βοΈ New AIP Canada Supplement (SUP) Detected
AIP SUP: SUP 037/2026
Published: 2025-05-14
Effective: 2025-05-19
Affected Location: Winnipeg / James Armstrong Richardson Intl (CYWG)
Type: Aerodrome Construction
FIR: CZWG (Winnipeg FIR)
π§ What Changed (Summary)
Introduces a planned multi-phase aerodrome construction program at Winnipeg / James Armstrong Richardson Intl (CYWG), with the supplement describing phases 1 through 5. The supplement states it is for situational awareness and that NOTAMs will be issued and take precedence.
- Total planned duration stated: 19 May 2026 0600 UTC to 30 Oct 2026 1800 UTC
- Planned number of phases: 5 (phases completed: 0 of 5 at publication)
- Legend indicates potential status/designations during phases: Closed (red), Runway available for taxi only (amber), Construction activity area (grey)
βοΈ General Aviation Impact (Highlighted)
Operational Notes:
- Expect runway/taxi routing changes and/or movement area restrictions during construction phases; use NOTAMs for current closures and operating limitations.
- Allow extra time for taxi and be alert for work areas, altered markings/lighting, and increased vehicle/equipment activity on/near manoeuvring areas.
VFR Impact:
- VFR arrivals/departures at CYWG may be affected by temporary runway/taxiway restrictions and changed ground movements during active phases; plan alternates and additional fuel/time margin.
π Official Source
ποΈ This summary is generated using automated analysis and may omit important details.
It does not replace the official NAV CANADA AIP SUP. Pilots must review the original notice in full prior to flight.